Technical Report - Quarter Ended 31st December, 2006
1.0 SUMMARY & COMMENTS
Macmin Silver Ltd (Macmin) is a silver focused company whose primary projects are the Texas Silver Project, S.E. Queensland, Australia where the Twin Hills Silver Mine is nearing production and the Tally Ho Project near Mackay, Central Queensland. Macmin has exposure to gold by way of an 18% equity in New Guinea Gold Corporation (NGG) and a 1% NSR royalty on production by NGG. In addition, Macmin maintains equity investments in junior Australian explorers, Malachite Resources NL and Frontier Resources Ltd.
  • Twin Hills Silver Mine commissioning proceeding according to plan; with 15,000 tonnes of crushed ore placed on leach pad.
  • Extensions to silver-zinc mineralisation in recent drilling at Tally Ho Silver Project; with resource definition drilling being planned.
  • New Guinea Gold plans for re-organisation of its exploration assets.

2.0 TEXAS SILVER MINES PTY LTD
The Texas Project (EPMs 8854, 11455, and 12858; ML 5932 and ML 50161) is located 100km west of Stanthorpe. Texas Silver Mines Pty Ltd is a wholly owned subsidiary of Macmin Silver Ltd.

2.1 Twin Hills (ML 50161)

2.1.1 Development/Commissioning Activities Summary.

Development to date has seen commissioning of the crushing, stacking and agglomerating circuit resulting in 15,081 tonnes of ore placed on the leach pad; storm containment dam wall construction reaching 16m above the floor of the dam, and construction of the under-drain for the waste rock dump started.
  • The Environmental Authority documentation currently being prepared by the EPA is in draft form and has been reviewed by Macmin. Changes were agreed to some sections, mainly to do with waste rock management, in order to more readily carry out the conditions. Macmin has not been made aware by the EPA of any further requirements for information or data to complete the document.
  • A Financial Assurance bond of $1,060,200 in the form of a bank guarantee has been lodged with the Department of Mines and Energy to cover the first year's rehabilitation commitments. This amount is substantially increased from the $145,000 bond required under the original mining lease conditions and represents the additional requirement by the EPA for covering the waste rock dumps and heap leach pad areas with a layer of clay and soil, which is then vegetated to provide a ‘store and release' cover. A ‘store and release' cover retains moisture close to the surface where vegetation can take it up and transfer it back into the atmosphere.
  • An under-drain beneath the waste rock dump area is being constructed to comply with environmental requirements to minimize any potential acid leachate emerging from the waste dump after rainfall events. The drain incorporates a catchment sump at the southern end, so that potential leachate can be pumped back into the processing circuit. 60 metres of under-drain has been completed to-date, which is sufficient to allow for the commencement of waste removal from the pit area. Until the present time, waste had been stock-piled within the pit area, while design issues and construction of the initial section of the drain were finalised.
  • Further blasting and excavation of the storm containment dam void will take place to increase the storage capacity of the dam and to provide a source of large unmineralised rocks used in the construction of the waste dump under-drain.
  • The commissioning of the crushing, agglomerating and stacking circuit continued during the quarter and to-date, 15,081 tonnes of material have been placed on the leach pad. This commissioning period provided training for the operators, who, as part of Macmin's employment policy, were recruited from the local area of Texas and thus not previously skilled in this type of equipment operation.
  • The processing ponds have now been covered with bird netting which was a condition prior to the use of cyanide on-site. Additional earthworks and HDPE lining required to complete pond spillways and bunding are now finished.
  • Cyanide awareness and handling training is about to be carried out by Orica, the supplier, and the first shipment of cyanide is scheduled for delivery to site on the 1st February 2007.
  • It is anticipated that the first 20,000 tonne heap will start irrigation in mid-February, so that leach solutions containing silver will be available in March to commission the EM-EW plant, which will produce silver powder.
3.0 EXPLORATION
3.1 Tally Ho Silver Project
During the quarter, exploration activity continued at Tally Ho with the completion of 17 drill holes and a ground magnetic survey. Further encouraging results were reported (ASX Release 23.1.07 attached) with drilling demonstrating that breccia hosted silver-zinc polymetallic mineralisation can be traced in excess of 200 metres in length. Further drilling is required to define the geometry of the mineralized zones.

Potentially economic intercepts of silver and polymetallic mineralisation have been encountered in many of the drill holes at Tally Ho. A major programme of drilling will commence in April with the aim of continuing to explore and define the mineralized system and to provide enough information to allow resources to be quantified.

During this quarter, an extensive soil geochemical sampling programme will be undertaken to obtain data on the extent of the outcropping mineralized breccia/intrusive complex.

All releases to the ASX can be viewed on the Macmin website, www.macmin.com.au. However, some of the more important releases in the third quarter of 2006 and the recent Tally Ho release dated 23 January 2007, are included in this report at Appendix A.

4.0 CORPORATE
During the quarter, the company made presentations at the ‘Stockday Conference' in Frankfurt (October 26-28) and in Munich at the International Precious Metals Show (November 23-24). These presentations in Germany provided the opportunity for the many European shareholders to discuss, with management representatives, the progress of Macmin's activities.

The company also made a presentation at the inaugural Silver Summit (UK) on November 9 in London with the purpose of promoting our activities to UK investors.

An Entitlements Issue to shareholders raised $8.62 million before costs in December. The Company wishes to thank all those shareholders who supported the Company in this Issue. Funds raised will be used for an aggressive exploration programme in 2007 on the Company's tenements.
5.0 INVESTMENTS
Macmin maintains equity investments in the following public companies with exposure to the precious and base metals sectors. Information and releases about these companies' activities can be found on each company's website.

Company
Shares
Options
Market Value
31 December 2006
New Guinea Gold Corporation (TSX)
www.newguineagold.ca
17,847,020
-
$8,741,352
Malachite Resources NL
www.malachite.com.au
1,500,000
-
$330,000
Frontier Resources Ltd
www.frontierresources.com.au
3,364,824
3,104,167
$581,521
6.0 NEW GUINEA GOLD
New Guinea Gold Corporation (17% Macmin) continued with exploration and mine development during the quarter and issued a number of announcements on encouraging exploration results, which can be viewed at www.newguineagold.ca. Two press releases, one on the Sinivit development schedule, and the other on the proposed reorganization plan for New Guinea Gold Property Assets are included in this report at Appendix B.

D.M. O'Neill
MANAGING DIRECTOR
This report is based on & accurately reflectsinformation compiled by a competent personas defined in Appendix 5A of the ASX Listing Rules

APPENDIX A
MACMIN SILVER LIMITED - ASX RELEASES

23rd January 2007
MACMIN ENCOUNTERS FURTHER SILVER - ZINC AT TALLY HO

Summary
In November 2006, Macmin carried out a programme of drilling comprising reverse circulation and diamond drilling. Assay results from the reverse circulation drilling were recently received.

Highlights of the drill holes are as follows:

GRRC26 - 14m (16-30m) @ 80g/t silver, 2.94% zinc

GRRC29 - 2m (76-78m) @ 507g/t silver, 1.07g/t gold, 23.3% zinc, 0.72% copper

GRRC30 - 26m (46-72m) @ 46g/t silver, 4.34% zinc, 0.18% copper
Including 8m (50-58m) 70g/t silver, 0.16g/t gold, 9.56% zinc, 0.28% copper

GRRC32 - 6m (52-58m) @ 126g/t silver, 0.13g/t gold, 4.23% zinc, 1.48% lead, 0.29% copper

The significance of the results from this drilling programme, in comparison to the initial successful drilling carried out by Macmin in August 2006, is that higher zinc values were encountered in several holes. Encouraging mineralised intercepts occurred in most holes, but particularly holes GRRC29, 30 and 32, which have demonstrated narrower high grade silver-zinc polymetallic zones which represent an additional target to the broader mineralised zones previously encountered in the breccia body.

Drilling
The drilling programme undertaken at the Tally Ho Silver Project near Mackay in Central Queensland was carried out in November, 2006. The assay results from the RC drilling of the programme were received in January 2007.

A total of 13 reverse circulation drill holes (1,842m) were drilled; 7 holes on the Tally Ho breccia and 6 holes on the Lily prospect (located about 500m north-east of the Tally Ho breccia).

Significant zones of silver-zinc mineralisation were encountered in the Tally Ho breccia (Table 1 - Drill results and Table 2 - Co-ordinates); but only anomalous values were encountered around the Lily Prospect.

In drill hole GRRC29, a 2m interval (76-78m) encountered 507g/t silver, 1.07g/t gold, 23.3% zinc and 0.72% copper. This high grade massive sulphide intercept represents a new target type hosted within or adjacent to the breccia body. Significant zinc was also encountered in GRRC30 where an 8m intercept (50-58m) encountered 70g/t silver, 0.16g/t gold, 9.56% zinc and 0.28% copper, within the breccia.

A drill section (Figures 1 & 2 Section A-A) at Tally Ho shows the continuity of mineralised breccia, detected thus far, along a 200m length. Although silver mineralised throughout the drilled section, it can be seen that the silver dominant polymetallic mineralisation in the south-west passes to a zinc rich polymetallic mineralisation towards the north-east, which is very encouraging for the economic potential of the project as the zinc component would represent a very significant by-product credit, should development of a silver mine be undertaken.

Macmin carried out a ground magnetic survey (Figure 3) in October 2006, which revealed the presence of an annular magnetic high response. The one diamond drill hole that has intersected this magnetic feature has encountered disseminated magnetite and magnetite veinlets which may represent hydrothermal alteration from a shallow high level intrusive.

A multi-purpose drill rig has been contracted to start a major drilling programme at Tally Ho in April. In the meantime, a soil geochemical survey will be carried out to obtain data on the extent of the outcropping mineralised breccia/intrusive complex, with the aim of providing additional drill targets.

***************************

An update on the commissioning of the Twin Hills Silver Mine will be provided in the Quarterly ASX report to be released prior to the end of January, 2007.

D.M. O'Neill
MANAGING DIRECTOR

The information in this report that relates to Exploration Results, Mineral Resources or Ore Reserves is based on information compiled by Denis O'Neill, who is a Member of The Australasian Institute of Mining and Metallurgy. Denis O'Neill is a full-time employee of the company.

Denis O'Neill has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Denis O'Neill consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

Table 1.





• Assays
*In ground
Value

Hole No.
Interval
From To
(m)
Length
(m)
Silver (g/t)
Gold
(g/t)
Zinc
(%)
Lead
(%)
Copper
(%)
Silver Equiv.
(g/t)
GRRC26
16 - 30
(incl 16 - 22)
30 - 70
(incl 60 - 70)
76 - 78
14
6
40
10
2
80
165
42
128
-
-
0.12
-
-
3.16
2.94
3.56
0.65
0.8
-
-
-
-
-
-
-
0.3
-
0.36
-
349
558
101
277
170
GRRC27
0 - 16
16
30
-
-
-
-
30
GRRC28
8 - 24
66 - 68
96 - 100 (EOH)
16
2
4
-
343
84
-
0.27
0.16
1.26
-
-
-
-
-
-
-
-
114
358
93
GRRC29
76 - 78
82 - 84
2
2
507
124
1.07
-
23.3
-
-
-
0.72
-
2,830
124
GRRC30
46 - 72
(incl 50 - 58)
76 - 96
100 - 102
26
8
20
2
46
70
39
163

0.16
-
-
4.34
9.56
1.22
0.78
-
-
-
-
0.18
0.28
-
-
479
1,007
150
233
GRRC31
50 - 56
60 - 72
74 - 76
80 - 82
90 - 92
6
12
2
2
2
91
116
20
73
34
-
-
-
-
-
1.6
2.0
1.93
0.49
3.5
0.4
-
-
1.07
0.12
0.19
0.18
-
0.27
0.13
288
336
193
207
379
GRRC32
52 - 58
(incl 56 - 58)
84-94
6
2
10
126
304
100
0.13
0.21
4.23
7.42
2.49
1.48
0.74
-
0.29
0.62
0.32
622
1,143
395
Notes:
  1. The silver equivalent values are tabulated, as silver is the metal of major economic significance encountered in the drill intercepts since the start of Macmin's drilling programme. The following metal prices were used in the calculation. Silver AUD$15/oz, copper AUD$4.66/lb, zinc AUD$2.00/lb, lead AUD$0.66/lb, gold AUD$800/oz. Silver equivalent values will change over time as any one or more metal prices change and are presented to give an indicative guide only.
  2. True widths of the intervals quoted are not listed, as the orientation of the mineralised zone is uncertain.
DRILLING AND SAMPLING DETAILS

All samples were collected as percussion chips/dust from the reverse circulation drilling rig. Assay samples were collected over 2m intervals through the mineralised zones and over 4m intervals through the visually non-mineralised zones.

As part of the Company's quality control programme, a duplicate sample is collected about every 20 samples and submitted under a different sample number providing a check on repeatability.

Assaying is carried out by ALS Chemex in Brisbane using the ICP technique for silver, copper, lead, zinc, arsenic, antimony, bismuth and molybdenum. Gold is assayed by the ICPMS technique.

Table 2. Co-ordinates (Datum GDA94)

Hole No.
Easting
MGA

Northing
MGA

RL
DIP
AZI MAG
AZI GRID
Depth (m)
GRRC026
688845
7632882
267.5
-50
206
215
154
GRRC027
688871
7632885
265
-50
270
279
154
GRRC028
688896
7632885
260
-50
330
339
100
GRRC029
688797
7632818
300
-60
71
80
154
GRRC030
688795
7632822
300
-60
43
52
154
GRRC031
688790
7632817
300
-75
204
213
154
GRRC032
688791
7632819
300
-90
0
0
154


Tally Ho Project
Tally Ho Project
Tally Ho Project

1 December 2006
REVISED EPA APPROVAL DATE FOR TWIN HILLS

The Chairman's address to the Company AGM on Tuesday stated "We believe we have now complied with all requirements of the EPA and expect final approval by the end of 2006". This was based on a decision date of 2 December 2006 previously advised by the EPA in respect of the draft Environmental Authority.

We have today received a ‘Notice of extension of time for decision', which moves the decision date to 2 March 2007. In that notice the EPA advise that "additional time is necessary to allow for the preparation and review of the draft Environmental Authority".

Along with the Notice, the EPA have supplied a preliminary draft Environmental Authority and advise that they are working on further non-standard conditions to be included in the final draft Environmental Authority. The EPA also advise "it is anticipated this entire period (to 2 March 2007) will not be required to finalise the Environmental Authority".

The Company is actively working with the EPA and our environmental consultants to finalise requirements and ensure that the delay (if any) in silver production will be minimal. In the meantime, we are confident that staff and equipment at the site can be productively employed in ongoing site works and commissioning activities.

G.M. Edwards
COMPANY SECRETARY

28th November 2006
CHAIRMAN'S ADDRESS

Welcome to the 14th AGM of Macmin Silver Ltd.

I am pleased to be able to report to you that we are on track to produce silver in the first quarter 2007. 2006 has been a successful year in terms of the share price with the price rising from 15 cents in November last year to a high of 44 cents in July when silver peaked at just under $US15/oz and is now sitting around 30 cents with silver over US$13/oz. When silver exceeds its high of US$15/oz I believe we can expect the share price to test its previous high of 44 cents.

In terms of mine development, 2006 has been difficult and we have to note with regret that production has been delayed until early 2007.

The delays in proceeding to production were many and largely caused by three factors - initially the weather, then difficulty in obtaining some equipment due to the high level of activity in the industry and finally due to more rigorous requirements and studies by the Environmental Protection Agency (EPA) than we had expected. As of today the construction is nearing completion with only construction of the storm water dam wall and waste rock dump drainage system to be finished to EPA requirements.

Plant commissioning of the crushing, agglomerating and heap stacking system have commenced. The electrowinning circuit is ready for wet commissioning.

We believe that we have now complied with all requirements of the EPA and expect final EPA approval by the end of 2006. This will allow us to almost immediately commence processing of silver ore with silver production thereafter.

Over the succeeding few months we expect that silver production will gradually be increased to the initial expected annualised rate of 2.5M ozs/year. If silver exceeds US$15/oz next year we will look at increasing production further.

There are some unresolved points - notably whether we choose to sell our silver product directly or whether we decide to have it refined to silver bullion or a combination of both. We have formed a sales committee to follow this through but it probably cannot be resolved until we produce sufficient powder to allow end users to determine if it suits their needs.

Exploration has been fairly low key throughout 2006, but we had a very significant discovery at Tally Ho in central/east Queensland. As a result of this discovery and our desire to fully optimise exploration opportunities in the Texas area we recently decided that we should very substantially increase exploration in the near term - thus the reason for the current Rights Issue. We also have zinc potential we would like to pursue at the Silver Spur prospect at Texas. We take the view that the silver price is likely to be higher in 2007. We want to have a much greater exploration program in progress when this happens to take advantage of the likely enthusiasm for silver at that time. We considered we should not wait until mid 2007 to be able to substantially increase our exploration budget. With the funds raised by the Rights Issue we will also be able to look at other opportunities to expand your company.

In terms of investments, New Guinea Gold, Malachite and Frontier are all generating positive exploration results with New Guinea Gold looking especially attractive.

The final point I would like to make is the very substantial backing the company gets from European investors. Over 40% of our shares are held by shareholders who reside in Germany and Switzerland.

Before closing I would like to introduce Bill Guthrie who is the General Manager of the Texas Project and extend my thanks to director Ed Newman who has worked tirelessly at Texas and to our Managing Director Denis O'Neill for his excellent leadership.

In closing I wish all shareholders a Prosperous 2007 and thank you for your support over the past years.

R.D.McNeil
CHAIRMAN

APPENDIX B
NEW GUINEA GOLD CORPORATION - TSX RELEASES

SINIVIT DEVELOPMENT SCHEDULE

Vancouver 8th December, 2006 New Guinea Gold Corporation ("NGG" or "the Company") reports significant progress has been made at the Sinivit Project. Facilities at site and operational now include an 80 man camp, office, logistics organization, all necessary mobile equipment, mining contractor and mining equipment, vehicles, explosives magazine, cyanide storage area, maintenance facilities, sample preparation facilities, all mine roads including mine haul roads, crushing plant and gold extraction plant. The surface of the mineralized zone has been benched for initial mining, grade control has been completed over surface exposures and grade control drilling using the RC rig has commenced. The crushing plant will commence commissioning in January and mining of gold mineralized rock and waste has already commenced.

A detailed assessment of the development progress at the Sinivit Mine Project in Papua New Guinea (PNG) was recently concluded, by technical staff from associate company, Macmin Silver Ltd, and has resulted in a detailed amended schedule to gold production.

A myriad of minor delays have been experienced over the past two months, mainly as a result of the following:

  • normal start up problems;
  • the remote (but accessible) nature of the site;
  • delays in shipping within PNG and from Australia to PNG;
  • training of new staff; and
  • delays inherent in constructing mines in developing countries such as PNG.
Safety considerations in the construction of the vats and the use of cyanide at site for processing has prolonged the construction of the vats. These vats are being built to tailings dam standards to ensure absolute safety. In fact the crushed gold mineralised rock being processed is physically quite stable compared to conventional mine tailings. It consists of sand to pebble size particles which will assume a stable angle of repose at all times in comparison with tailings which can act as a fluid. In addition the vats are fully lined with special purpose, high density plastic liners which are fitted by specialists. These specialists are in high demand at the present time. This industry-wide shortage of specialized technical professionals has an impact on the progress of construction schedules, however, this work is now well advanced and the first two vats are scheduled for completion, including lining by early March 2007.

Chairman and CEO Bob McNeil stated "Although development of the Sinivit Project is proceeding somewhat slower than we had planned there are no major impediments to gold production in the near future. Mining has commenced and crushing will commence in due course. It will take approximately 6 to 8 weeks to crush a sufficient supply of gold mineralized rock in order for processing to commence. At present gold prices of over AUD$800/oz, the Sinivit project is very robust and will provide a very strong foundation for continued expansion of the Company ."

The schedule to gold production is now as follows:
  • Mining of waste and gold mineralised rock has commenced with gold mineralised rock being stockpiled as well as waste which is used in the construction of the vat containment walls. The crushing plant is erected and will commence commissioning, using stockpiled gold mineralised rock, in early January. Full scale mining and crushing should be underway in February with the stockpiling of crushed ore for processing in the first vat.
  • Vat construction is well underway with sub-surface drainage and monitoring systems in place. Earthworks for Vat 1 will be completed in late January and Vat 2 in late February. Vats 1 and 2 will be lined in late February with completion expected in early March 2007.
  • Stockpiled, crushed, gold mineralised rock will be loaded into Vat 1 in early March 2007 and processing is expected to commence in mid March with gold dore to be produced soon thereafter. Vat 2 is scheduled to be loaded and processing commenced by early May 2007.
The above dates should be regarded as approximate and management will endeavor to shorten time frames if possible. The schedule is regarded as realistic, but unforeseen events could still influence, or extend, completion dates.

NGG has a comprehensive drilling program in place for 2007 to define gold resources at other key gold properties, Normanby (Imwauna), Mt Penck, and Sehulea (Weioko). See also www.newguineagold.ca

For further information contact Forbes West toll free at 888 655 5532, email forbes@sherbournegroup.ca or Judith O'Quinn at 604 662 3598, email ngg@telus.net
The technical data in this release was prepared by or under the supervision of Robert D. McNeil, CEO of New Guinea Gold Corporation. Mr McNeil has an MSc in Geology, 44 years mining industry experience, is a Fellow of the Australian Institute of Mining and Metallurgy, and meets the requirements of NI 43-101 for a qualified person.

ON BEHALF OF THE BOARD

"R.D.McNeil"
CHAIRMAN & CEO

The TSX Venture Exchange has not reviewed and does not accept the responsibility of the adequacy of this release. The statements made in this News Release may contain certain forward-looking statements. Actual events or results may differ from the Company's expectations. Certain risk factors may also affect the actual results achieved by the Company.
PROPOSED RE-ORGANISATION PLAN FOR NEW GUINEA GOLD PROPERTY ASSETS

Vancouver, 16th November 2006New Guinea Gold Corporation (the "Company" or "NGG") holds interests in ten gold properties and two porphyry copper/gold/molybdenum properties in Papua New Guinea. The Company is focussing on gold - developing the Sinivit property (92.5% NGG) and defining resources on the Normanby property (Imwauna Project - 100% NGG), Sehulea Property (100% NGG), and Mt Penck Project (60% NGG). Although exploration is proceeding on all 12 properties, the financial resources of the company has not permitted exploration to proceed at a pace warranted by the potential of the remaining properties and present metal prices. The Company needs to obtain better value for shareholders from these assets.

Management, our investment advisers and some major shareholders are of the opinion that the present share price and market capitalisation of the Company only reflects the few key properties on which exploration/ development is currently focussed and does not factor in a value for most of the remaining properties.

Seven properties are being considered as part of the re-organisation and of these seven properties six are held in conjunction with Vangold Resources Ltd. The Boards of Directors of the partners are pleased to announce that their respective management teams are preparing a proposal for the re-organisation of mineral property assets currently held by Kanon Resources Ltd (Kanon), the Simuku porphyry copper/gold/molybdenum system held by NGG (90%) and Yeaman (10%) and the Mt Nakru porphyry copper/gold/molybdenum system held by NGG 50% and Kanon (50%). Kanon is owned 50% NGG and 50% Vangold. Each of the respective Boards of Directors have instructed their management teams to negotiate the terms of the re-organisation, review financing sources and nominate Boards of Directors.

The terms of the re-organisation are subject to the necessary financing and the respective Board's, shareholder, regulatory and statutory approvals.

The re-organisation will allow NGG to focus more closely on its three key gold properties, Sinivit (NGG 92.5%), Normanby (Imwauna 100% NGG), and Sehulea (Weioko 100% NGG). NGG will also retain its interests in J/V properties Feni and Crater Mountain. The re-organisation should allow a substantial increase in drilling activity at the key properties.

The "spin off" companies being considered for the re-organisation are:
  • The first company would be Kanon Resources properties which include the Mt Penck, Allemata, Bismarck, Fergusson and Yup River properties.
  • The second company would include the 90% NGG, 10% Yeaman owned Simuku porphyry copper/gold/molybdenum property and the jointly held (Kanon 50%, NGG 50% giving NGG an effective 75% interest). Yeaman has indicated an interest in extending an option on his 10% carried interest in Simuku to NGG.
All properties in the proposed "spin off" are described in detail (including NI 43-101 reports) at www.newguineagold.ca

Mr Bob McNeil, Chairman and CEO of NGG states: "We all believe that the best way to benefit our respective shareholders is by transferring these highly prospective mineral property assets into the two new entities. Our Board is considering how shareholders can gain most benefit from the reorganization. Our preference is to distribute some or all of the interest retained by NGG directly to shareholders in proportion to their holding in NGG but I must emphasize that at this time the Board has not made a final decision. If this reorganization is approved, it will allow us to increase our activities on these projects without further major dilution of each company's shares. For example, we would expect to increase the current expenditures at Mt Penck by at least 100%, add additional drills to the program and also start a drilling program to define resources at the copper properties. I believe this will be a great opportunity for our shareholders."

Mr. Dal Brynelsen, President and CEO of Vangold commented on the re-organisation by stating, "This is the first major step forward for Vangold's large portfolio of projects. Our mandate has always been to create solid, viable entities from our diverse projects directly enhancing shareholder value. This particular combination of properties will allow both new companies the opportunity to become such entities. The new companies will be well financed with a strong balance sheet and no debt. This will ensure that exploration and development can be expedited on a more timely schedule, with the aim of meeting our common goal that of furthering development and adding to the value of these important assets. I agree with Bob that Vangold would also look to distributing some or all of the interest retained by Vangold directly to shareholders in proportion to their holdings in Vangold."
.

NGG is also developing a gold project at the Sinivit property in Papua New Guinea and is currently engaged in resource definition drilling at the Imwauna Gold Project. NGG expects to commence drilling at the Weioko Project in the near future and recently completed a drilling program to test molybdenum potential at Simuku (results pending).

Drilling continues at Mt Penck and will commence at Mt Nakru in the near future.

In other PNG projects, recent field sampling and mapping at the Feni Project has defined a three square kilometer area within the former Ambitle Volcano collapse which warrants drill testing for Lihir style gold mineralisation (News Release 7 November, 2006). The Feni Project is presently held 50/50 by Vangold and NGG with Vangold retaining the right to acquire a further 25% interest.

For further information contact Forbes West toll free at 888 655 5532, email forbes@sherbournegroup.ca or Judith O'Quinn at 604 662 3598, email ngg@telus.net

The technical data in this release was prepared by or under the supervision of Robert D. McNeil, CEO of New Guinea Gold Corporation. Mr McNeil has an MSc in Geology, 44 years mining industry experience, is a Fellow of the Australian Institute of Mining and Metallurgy, and meets the requirements of NI 43-101 for a qualified person.

ON BEHALF OF THE BOARD

"R.D.McNeil"
CHAIRMAN & CEO

The TSX Venture Exchange has not reviewed and does not accept the responsibility of the adequacy of this release. The statements made in this News Release may contain certain forward-looking statements. Actual events or results may differ from the Company's expectations. Certain risk factors may also affect the actual results achieved by the Company.
Appendix B
Appendix B
Appendix B
Appendix B
Appendix B